Western European
Nuclear
Regulators' Association
Nuclear safety
in
EU candidate
countries
October 2000
TABLE OF CONTENTS
Foreword
General
conclusions of WENRA on nuclear safety in EU candidate countries
Report
Executive
summaries
Bulgaria
Czech
Republic
Hungary
Lithuania
Romania
Slovakia
Slovenia
Detailed
chapters
Bulgaria
Czech Republic
Hungary
Lithuania
Romania
Slovakia
Slovenia
Annex 1:
generic
safety characteristics and safety issues for RBMK reactors
Annex 2:
generic
safety characteristics and safety issues for VVER reactors
FOREWORD
The Western European Nuclear Regulators'
Association
(WENRA) is the association of the Heads of nuclear regulatory
authorities
of Western European countries with nuclear power plants, namely
Belgium,
Finland, France, Germany, Italy, the Netherlands, Spain, Sweden,
Switzerland
(*)
and the United Kingdom. The association has the following objectives:
-
To develop a common approach to nuclear
safety and
regulation, in particular within the European Union,
-
To provide the European Union with an
independent
capability to examine nuclear safety and regulation in candidate
countries,
-
To evaluate and achieve a common approach to
nuclear
safety and regulatory issues which arise.
Nuclear safety in the candidate countries to the
European Union is a major issue that needs to be addressed in the
framework
of the enlargement process. Therefore WENRA members considered it was
their
duty to offer their technical assistance to their Governments and the
European
Union Institutions. They decided to express their collective opinion on
nuclear safety in those candidate countries having at least one nuclear
power plant: Bulgaria, the Czech Republic, Hungary, Lithuania, Romania,
Slovakia and Slovenia.
The report is structured as follows:
-
A foreword including background information,
structure
of the report and the methodology used,
-
General conclusions of WENRA members
reflecting their
collective opinion,
-
For each candidate country, an executive
summary,
a chapter on the status of the regulatory regime and regulatory body,
and
a chapter on the nuclear power plant safety status.
Two annexes are added to address the generic
safety
characteristics and safety issues for RBMK and VVER plants. The report
does not cover radiation protection and decommissioning issues, while
safety
aspects of spent fuel and radioactive waste management are only covered
as regards on-site provisions.
In order to produce this report, WENRA used
different
means:
-
For the chapters on the regulatory regimes
and regulatory
bodies, experts from WENRA did the work,
-
For the chapters on nuclear power plant
safety status,
experts from WENRA and from French and German technical support
organisations
did the work,
-
Taking into account the contents of these
chapters,
WENRA has formulated its general conclusions in this report.
WENRA's methodology for reaching the collective
opinion
expressed in the general conclusions has been to compare the current
situation
in the candidate countries to that in Western European countries using
a common format which is reflected in the structure of the chapters.
All
major safety issues identified in past international co-operation have
been considered. For each candidate country, a comparison was made with
the current Western European practices and, whenever appropriate,
discrepancies
or deficiencies were clearly identified.
WENRA has not made a detailed safety
assessment
of the different nuclear power plants. Nuclear safety is a national
responsibility
and it belongs to the regulatory body of the various candidate
countries
to regulate the safety of all nuclear installations on their national
territory,
in line with the national legislative and regulatory framework.
WENRA's collective opinion on the regulatory
systems
is based on generic preconditions for an independent and strong
regulatory
regime such as a comprehensive nuclear legislation, the existence of an
adequate licensing system, appropriate resources and technical support.
WENRA's collective opinion on nuclear power plant safety is based on
widely
applied standards in Western European countries for the
defence-in-depth
and associated barriers. Quantitative comparisons of probabilistic
safety
assessments have not been used as the available results are of
different
depth and quality.
A first version of this report was issued in
March
1999. It was solely based on the direct evidence WENRA had gathered
through
the different activities of its members (participation in multilateral
assistance programmes, and in particular the Phare programmes and the
IAEA
extra-budgetary programme, and in bilateral contacts). In particular,
information
necessary to formulate an opinion on the regulatory regimes and the
regulatory
bodies were in many cases derived from the regulatory assistance
projects
of the RAMG implemented under the Phare programme. With regards to the
safety status of nuclear power plants, WENRA had to recognise that in
some
cases the direct information was not sufficient to formulate an opinion.
For the present version, WENRA took the
appropriate
steps to collect the necessary information. In addition to the direct
evidence
already available, supplementary information was gathered through
meetings
with the candidate countries' regulatory bodies and plant operators. In
particular, an ad-hoc Task Force was established to gather and evaluate
additional information on VVER-440/230 reactors.
GENERAL
CONCLUSIONS OF WENRA
ON NUCLEAR SAFETY IN CANDIDATE
COUNTRIES TO THE EUROPEAN UNION
We, Heads of the Nuclear Regulatory
Authorities
assembled in WENRA, considering the status achieved on nuclear safety
in
the candidate countries to the European Union and taking into account
the
results of the investigations of experts from WENRA and from French and
German technical support organisations, come to the following
conclusions:
BULGARIA
Status of the regulatory regime and
regulatory
body
At present, the regulatory regime is not in line with Western
European
practice because it does not provide sufficient independence to the
regulatory
body. The resources of the regulatory body are also insufficient to
allow
it to carry out its responsibilities.
Nuclear power plant safety status
Kozloduy units 1-4 (VVER-440/230)
Although improvements have been made, the Kozloduy 1-4 units have not
reached an acceptable level of safety. Among others, a concern remains
about the ability of the confinement system to cope with the failure of
the large primary circuit pipework. Even if a solution could be found
to
this issue, significant time and effort would be required to achieve
the
necessary improvements to bring them up to equivalent Western European
reactor standards. The Bulgarian Government has announced its decision
to close down Kozloduy units 1-2 before 2003.
Kozloduy units 5-6 (VVER-1000/320)
If their modernisation programmes are carried out properly, the
Kozloduy
5-6 units should reach a level of safety comparable to that of Western
European reactors of the same vintage.
CZECH
REPUBLIC
Status of the regulatory regime and
regulatory
body
The regulatory regime and regulatory body in the Czech Republic are
comparable with Western European practice. A well-defined licensing
process
according to Western practice is in place.
Nuclear power plant safety status
Dukovany units 1-4 (VVER-440/213)
Already in the early years of operation, improvements were implemented
to remove safety deficiencies of the original design. An extensive
modernisation
programme has been established and it will allow Dukovany units 1-4 to
reach a safety level comparable to that of Western European reactors of
the same vintage. All issues, except the modernisation of the
Instrumentation
and Control systems, will be completed by 2004.
Temelin units 1-2 (VVER-1000/320)
The safety improvement programme for Temelin units 1-2 is the most
comprehensive one ever applied to a VVER-1000 reactor. Standard Western
practices were used to integrate Eastern and Western technologies and
to
deliver the corresponding authorisations. The on-going commissioning
process
has to confirm the integration of the different technologies. A few
safety
issues still need to be resolved. If these are resolved, Temelin units
1-2 should reach a safety level comparable to that of currently
operating
Western European reactors.
HUNGARY
Status of the regulatory regime and
regulatory
body
The regulatory regime and regulatory body in Hungary are comparable
with Western European practice. A well-defined licensing process
according
to Western practice is in place.
Nuclear power plant safety status
Paks units 1-4 (VVER-440/213)
A major safety improvement programme has been implemented at Paks units
1-4, bringing these units to a safety level that is comparable to that
of Western European reactors of the same vintage. An extensive
modernisation
of the Instrumentation and Control system is underway for further
enhancement
of safety.
LITHUANIA
Status of the regulatory regime and
regulatory
body
The legal and regulatory system has substantially developed over the
past years. A licensing system is in place. However, further efforts
are
needed to reach a level comparable to Western European practice. In
particular,
the legal status of the plant need to be changed in such a way that
operating
organisation is given full responsibility and authority for the safety
of the plant. The resources and technical support of the regulatory
body
need to be strengthened and its independence need to be maintained in
the
ongoing reorganisation of governmental institutions.
Nuclear power plant safety status
Ignalina units 1-2 (RBMK 1500)
The Ignalina units 1-2, although they have been much improved, cannot
realistically reach a safety level comparable to that of Western
European
reactors of the same vintage. A decision has already been taken to
shutdown
unit 1 before 2005. The current financial situation of the plant needs
to be improved in order not to delay the ongoing safety improvement
programme.
ROMANIA
Status of the regulatory regime and
regulatory
body
Romania is taking the appropriate steps to establish a regulatory
regime
and regulatory body comparable with Western European practice. Further
efforts are needed to ensure the necessary safety assessment
capabilities,
to develop the emergency response organisation within the regulatory
body
and to revise the pyramid of regulatory documents.
Nuclear power plant safety status
Cernavoda unit 1 (Candu 6)
The Candu 6 reactor of Cernavoda is similar to those in operation at
Gentilly 2 and Point-Lepreau in Canada. The main concern is with the
financial
situation of the plant: under the current situation, the plant
management
may have serious difficulties in ensuring and maintaining an adequate
level
of safety.
SLOVAKIA
Status of the regulatory regime and
regulatory
body
The regulatory regime and regulatory body in Slovakia are comparable
with Western European practice. However, the human and financial
resources
of the regulatory body need to be further improved in order to provide
reasonable work conditions for the staff.
Nuclear power plant safety status
Bohunice V1 (VVER-440/230)
A major upgrade programme is nearing completion, which has made
significant
improvements to reactor safety. A concern remains about the ability of
the confinement system to cope with the failure of the large primary
circuit
pipework. If a solution can be found to this issue, the plant should
reach
a safety level comparable to that of Western European reactors of the
same
vintage. The Slovak Government has announced its decision to close down
these units in 2006 and 2008.
Bohunice V2 (VVER-440/213)
Since 1990, significant improvements have been implemented at Bohunice
V2 (units 3-4). Once the on-going upgrading measures have been
implemented,
i.e. around 2002, the safety level of these units is expected to be
comparable
to that of Western European reactors of the same vintage.
Mochovce units 1-2 (VVER-440/213)
Compared to earlier reactors of the same type (VVER 440-213), the
Mochovce
units 1-2 included several modifications already at the design stage.
Although
some residual work is still needed to confirm all parts of the safety
analysis,
the safety level of the Mochovce units 1-2 is comparable to that of
nuclear
power plants being operated in Western Europe.
SLOVENIA
Status of the regulatory regime and
regulatory
body
In order to be fully comparable with Western practice, the nuclear
legislation
needs to be revised, addressing the identified deficiencies. The
regulatory
body has evolved and operates in general accordance with Western
practice
and methodologies, however the budget and financial situation need to
be
improved in order to increase its independent safety assessment
capability.
Nuclear power plant safety status
Krško (Western PWR)
The Krško plant is a Western design pressurised water reactor and its
safety level is comparable with that of nuclear power plants in
operation
in Western European countries. A large modernisation programme has been
recently completed. The safety implications of the long-term plant
ownership
need to be assessed. In addition, the evaluation of a few technical
issues
needs to be finalised.
J.P.
SAMAIN
Director General
Federal Agency for Nuclear Control
(FANC/AFCN)
Belgium |
J.
LAAKSONEN
Director General
Radiation and Nuclear Safety Authority
(STUK)
Finland |
A.C.
LACOSTE
Director
Nuclear Installation Safety Directorate
(DSIN)
France |
W.
RENNEBERG
Director General for Nuclear Safety
Federal Ministry for Environment, Nature
Conservation and Nuclear Safety (BMU)
Germany |
R.
MEZZANOTTE
Director, Department of Nuclear Safety and
Radiation
Protection
National Agency for Environment Protection
(ANPA)
Italy |
R.J.
VAN
SANTEN
Director
Nuclear Safety Department (KFD)
Ministry of Housing, Spatial Planning and
Environment
The Netherlands |
J.M.
KINDELAN
Chairman
Nuclear Safety Council (CSN)
Spain |
J.
MELIN
Director General
Swedish Nuclear Power Inspectorate (SKI)
Sweden |
L.
WILLIAMS
HM Chief Inspector Nuclear Installations
(HSE)
United Kingdom |
|
REPORT
Executive
summaries
BULGARIA
Status of the regulatory
regime
and regulatory body
Since the early 1990s, there have been
significant
improvements in the legislative basis and in the capabilities of the
nuclear
regulatory body (the Committee on the Use of Atomic Energy for Peaceful
Purposes - CUAEPP).
However, much remains to be done to bring the
regulatory regime up to Western European standards. The Bulgarian
Governments
needs to enact legislation that will make explicit the independence of
the CUAEPP from bodies concerned with the promotion of nuclear power.
The
government needs to provide adequate funding to the CUAEPP to enable
the
recruitment and retention of adequate numbers of qualified staff.
Funding
is also needed to enable the development new technical support
facilities
for the CUAEPP. Resources need to be committed to the drafting and
introduction
of necessary new and revised legislation.
Nuclear power plant safety
status
There have been significant improvements in
the
standards of operational safety at all units and staff awareness of
safety
issues has demonstrably increased. However, the lack of Safety Analysis
Report of any Bulgarian nuclear power plant is a serious shortcoming
for
judging the safety. Therefore to confirm the improvements implemented a
consistent safety case has to be established and it has to be reviewed
by the CUAEPP.
Kozloduy 1-4
Despite the significant safety improvements
already
achieved considering the present safety status of the plant, there are
still some major safety issues which are closely linked to the original
basic design of the VVER-440/230 reactors and which are difficult to be
removed, such as the limited confinement function and capability and
the
vulnerability against common cause failures. The work at Kozloduy is at
least three years behind that at Bohunice and consequently safety
improvement
is not as far advanced. At present in view of the large amount of work
required to be carried out it is difficult to have a final judgement on
the adequacy and feasibility of all measures foreseen. It seems,
however
that financial provisions for continued safety improvements are
inadequate.
For Kozloduy 1 and 2 the implementation of relevant measures cannot be
expected taking into account the announced closure dates.
Kozloduy 5-6
An extensive programme for further upgrading
of
these units with assured financing has been reviewed by Western TSOs
and
is at an early stage of implementation. Safety assessments done by
Western
TSOs for similar plants indicate that with the completion of the
planned
safety upgrades, it could be possible to achieve a level of safety for
units 5 and 6 which is in line with international recognised safety
practices.
CZECH
REPUBLIC
Status of the regulatory
regime
and regulatory body
The nuclear legislative framework in the Czech
Republic is comparable with Western European practice. It is considered
that the SÚJB has a status comparable to that of Western
European
regulatory bodies. The SÚJB has developed a series of regulatory
practices, including a well-defined licensing process, which compare
favourably
with those of Western European nuclear regulators.
Further improvements could arise from the
following
suggestions. It is recommended that the Government of the Czech
Republic
consider giving high priority to the implementation of the new Act on
emergency
preparedness and planning. The SÚJB should be asked to make
proposals
in view of removing too detailed requirements from the high level
documents
of the regulatory pyramid. Also, the contracting rules of the
SÚJB
need to be adapted so that it can obtain, when appropriate, the
necessary
high quality technical support on a long term basis.
Nuclear power plant safety
status
Dukovany NPP
In the early years of operation, modifications were carried out to
remove
safety deficiencies in the original design. An extensive modernisation
programme, called MORAVA, will be implemented by 2004 with the
exception
of I&C replacement.
The safety culture appears to be adequate. Safety assessments and
verification
documents, e.g. periodic safety reviews, are conducted in a way which
is
comparable to Western practice.
After full implementation of the modernisation programme it is
expected
that Dukovany NPP will achieve a safety level comparable to that of
NPPs
of the same vintage operating in Western Europe.
Temelin NPP
The safety improvement programme for Temelin NPP is the most
comprehensive
which has been applied to a VVER-1000/320 plant.
International co-operation has had a considerable influence on the
plant’s
safety improvements (design, operation, safety approvals), and on the
development
of safety culture.
The combination of Eastern and Western technologies was successfully
managed. Interfaces between the different technologies were considered
throughout the modernisation programme and a standard Western practice
was used to combine Eastern and Western technologies. The commissioning
process will need to confirm the integration of the different
technologies.
Some safety issues still need further clarification but if these
issues
are resolved, Temelin NPP will achieve a safety level that is
comparable
to that of operating Western PWRs.
HUNGARY
Status of the regulatory
regime
and regulatory body
The Hungarian approach to the licensing,
regulation
and control of nuclear facilities has developed strongly in the last
ten
years. A proper licensing process is in place, legislation and
regulations
are up-to-date, and the Hungarian regulatory practices are comparable
with
those of Western European countries.
However, there are some issues that need
further
consideration by the Hungarian Government. These are:
-
The fact that the Minister of Energy Affairs
is also
the HAEC President creates an apparent conflict of interest, even
though
the formal mandate of HAEC President precludes this,
-
The number of different authorities with
direct responsibilities
in the regulation of nuclear facilities increases the risk that
important
issues may be overlooked and reduces the efficiency of the regulatory
work.
The NSD needs to continue its efforts to develop
the inspection approach towards process oriented comprehensive team
inspections.
Nuclear power plant safety
status
The basic technical structure of Paks NPP is
good
from the safety point of view and the key safety systems are comparable
to Western plants of the same vintage. No major shortcomings in the
present
safety systems have been identified in any of the several, independent,
in-depth assessments done so far. Also the performance of the bubbler
condenser
containment in the case of large break LOCA has been verified in
full-scope
tests. There is still need for detailed analysis of the experimental
results
and for complementary tests of other design basis accidents (steam line
break and small LOCAs). Paks containment structures provide adequate
protection
against design basis accidents, and the overall radioactive releases
would
not be higher than what is accepted within the EU. However their leak
rates
are somewhat higher than those that are typical of Western European
reactor
containments.
Operational safety aspects are generally
comparable
to Western plants of the same vintage. However, management changes
related
to the political changes in the Government cause some concern. Periodic
safety reviews are conducted in line with Western practices and have
already
led to an increase in safety.
It is expected that after the implementation
of
safety improvements already scheduled, the plant will reach a level of
safety that compares favourably with plants of the same vintage in
Western
Europe.
LITHUANIA
Status of the regulatory
regime
and regulatory body
The legal and regulatory system has developed
substantially over the last years. A licensing system is in place and
the
regulatory body VATESI has developed its approaches to safety
assessment
and inspection. Further efforts are needed, however, in order to be
comparable
with Western European practice.
The Lithuanian government needs to consider
the
legal status of Ignalina NPP, in order to give the operating
organisation
the full responsibility and authority to handle all financial and other
management issues and thus to make the organisation able to take the
full
responsibility for safety. The legal obligation of VATESI to formally
license
suppliers needs to be changed, given a reasonable transition period.
The
imposed reduction of resources to VATESI, in terms of budget and staff,
needs to be compensated as soon as possible and the resources
successively
strengthened in order for VATESI to handle all normal regulatory tasks
and to contract the necessary technical support. In the reorganisation
under way, of governmental institutions reporting directly to the Prime
Minister, special attention needs to be given the independence of
VATESI.
VATESI needs to give high priority to the
development
of the internal Quality Management system and take the final steps in
separating
the roles of the regulatory body and the operator in all supervisory
activities.
Nuclear power plant safety
status
The two units of Ignalina NPP (INPP) belong to
the more advanced and improved design generation of RBMK reactors. In
addition,
the original design has been considerably improved through different
safety
improvement programmes. Most of the generic safety concerns with RBMK
reactors
have been satisfactorily addressed. More measures will be implemented,
for instance the installation of a new diversified and independent shut
down system at unit 2. However, weaknesses remain with respect to the
last
barrier for protection of the environment, especially in case of a
severe
accident. The weaknesses have to do with a less robust design of the
confinement
of the INPP reactors as compared with Western light water reactors. It
is not realistic to make the INPP confinement system comparable.
Consequently,
regarding mitigation of accidents, a safety level comparable to light
water
reactors of the same vintage in operation in Western Europe will not be
reached at Ignalina NPP. Therefore special attention needs to be given
the prevention of accidents during the remaining operating time,
including
the need to ensure a high level of operational safety.
The financial situation of INPP needs to be
much
improved in order to cover all operational expenses as well as
implementing
the safety improvement measures considered necessary for the remaining
operating time. Issues relating to safety culture need a stronger
implementation.
The symptom based emergency operating procedures need to be finalised
and
implemented without further delay. Due to the decision on
decommissioning
of unit 1, special attention needs to be given to keep a sufficient
number
of technical specialists, as well as maintaining the motivation of the
staff, for the remaining operating time of both reactors.
ROMANIA
Status of the regulatory
regime
and regulatory body
Romania is taking appropriate steps to
establish
a regulatory regime and a regulatory body comparable with Western
European
practice. Roles, duties and responsibilities of organisations involved
in nuclear safety are in line with those assigned to similar
organisations
in Western Europe. The independence of the regulatory body from the
organisations
involved in the use and promotion of nuclear energy is fully
established
by the law and is sufficiently reflected in the practice. The
regulatory
regime and the regulatory body have both improved during the licensing
process of Cernavoda NPP.
However some improvements are necessary to
reach
a situation comparable with the practice in Western European countries:
-
The independent assessment capability, the
inspection
practice and the technical support of CNCAN need to be strengthened.
The
salaries at CNCAN need to be further improved to preserve suitably
qualified
staff. Adequate resources need to be assigned to set up and implement a
training programme for new staff. Existing agreement with the Canadian
nuclear safety authority needs to be more effectively used for training
purposes and for seeking advice on regulatory issues specific of the
CANDU
technology. A strategic plan could support the assignment of existing
limited
resources to higher priority needs,
-
National organisations that would have a role
in
a nuclear emergency need to make their emergency procedures and lines
of
communication more effective. In addition, CNCAN needs to further
develop
its competence and staff numbers in this area and establish an
emergency
response centre,
-
The responsibility for auditing and approving
vendors
and suppliers should rest with the operating organisation and not with
the regulatory body.
Nuclear power plant safety
status
Romania has only one NPP into operation. It is
a CANDU 6 reactor similar to those in operation at Gentilly 2 and Point
Lepreau in Canada. The plant was constructed and commissioned under the
responsibility of a Western Consortium (AECL, Ansaldo). The Cernavoda
plant
managers and operators have a professional attitude and have
assimilated
a western safety approach and culture.
It is important that the Romanian Government
ensures
that the current financial problems of the utility do not affect the
ability
of the management to maintain an adequate level of safety at the plant.
Western support, especially from Canadian experts, should be made
available
when it is needed in the future.
Based on available information it is apparent
that additional assessments are needed to confirm design safety margins
against seismic events and the adequacy of fire protection. Also, the
resolution
of specific safety issues for similar plants that have been addressed
or
are currently under discussion in Canada need to be noted and
incorporated
where necessary into an improvement programme. The current high level
of
qualification and safety culture of the plant managers needs to be
preserved
in the longer tem. The plant management safety culture should be
extended
to all plant personnel and to the necessary service and support
interfaces
existing in the country. There is finally a need for improvement in
some
areas of plant operation such as training, emergency preparedness and
accident
management.
SLOVAKIA
Status of the regulatory
regime
and regulatory body
The nuclear legislative framework in Slovakia
is in line with Western European practice. The ÚJD has made
significant
progress over the recent years and has taken the appropriate steps to
develop
a series of regulatory practices comparable with those of Western
European
nuclear regulators. It is considered that, in general, the ÚJD
status
is comparable to that of regulatory bodies in Western European
countries.
On-going developments will improve its effectiveness.
It is recommended that the government of
Slovakia
consider the following suggestions. The ÚJD financial resources
need to be further increased, in particular but not only, to maintain
the
independent assessment capability which was initiated under Swiss
assistance.
In order to retain highly qualified staff, the salaries at the
ÚJD
need to be made comparable with those of the operator's staff. It is
suggested
that the government give a high priority to the adoption of the
national
emergency plan. Also, the Atomic Act should be amended to remove some
duties
of the ÚJD that are not directly dealing with nuclear safety.
Finally, it is recommended that the ÚJD
pay particular attention to ensure a clear separation between the
technical
support it receives and that provided to an operator.
Nuclear power plant safety
status
The safety of Slovakian nuclear power plants
has
been improved since the early 1990´s in a determined manner with
a strong national commitment, and significant investments have been
made
in technical upgrades. Guidance received from the IAEA has been used
efficiently.
Operational practices at all Slovakian nuclear power plants are
consistent
with those in Western Europe.
The following conclusions can be made:
Bohunice V1 (units 1-2)
The revised design requirements provide a
coherent
target for safety improvement of the plant. The utility has made
significant
progress towards establishing a new design base and implementing the
relevant
measures. Some work remains to be done but no technical obstacles in
completing
it are foreseen. It will be completed in 2000.
If a solution can be found to the concern
related
to the confinement ability to cope with the double ended guillotine
break
LOCA, the safety level of these units is expected to be comparable with
that of units of the same vintage in Western European Countries.
Bohunice V2 (units 3-4)
Since 1990, significant improvements have been
implemented at Bohunice V2. However, in order to achieve adequate
reliability
of safety systems in all operating situations, an extensive
modernisation
programme is planned for implementation between 1999-2006, with the
major
upgrades relating to safety being completed by 2002.
The safety of Bohunice V2 units seems
generally
adequate. Once the ongoing safety upgrades have been implemented (by
about
year 2002), the safety level of these units is expected to be
comparable
with that of units of the same vintage in Western European countries.
Mochovce (units 1-2)
Compared to their VVER-440/213 predecessors,
units
1 and 2 of Mochovce included several modifications during the design
phase.
The most important of these are the use of higher quality equipment and
the improvement of systems used in accident situations. However, some
design
weaknesses remained, and a dedicated nuclear safety improvement
programme
was developed for the Mochovce NPP in 1995. This programme, which is
almost
complete, was reviewed by Western European Technical Safety
Organisations.
Although some residual work (e.g. bubbler
condenser
qualification, Mochovce site seismicity characterisation) is still
needed
to confirm all parts of safety analysis, the safety level of Mochovce
units
is comparable to that of the nuclear power plants being operated in
Western
Europe.
SLOVENIA
Status of the regulatory
regime
and regulatory body
The Slovenian Nuclear Safety Administration
(SNSA)
operates, in general, according to Western practice and methodologies.
Since 1987, when the SNSA was established, it has evolved and matured
as
a regulator, with a clear separation between regulation and promotion
of
nuclear energy. The SNSA has a staff of motivated and dedicated persons
with competence in their areas of responsibility. The SNSA has been
assigned
most of the roles and responsibilities normally allocated to a
regulatory
body. However, there are some issues that need to be addressed.
It is recommended that the Government of the
Republic
of Slovenia addresses the fact that the existing legislation on nuclear
and radiation safety is not fully in line with current Western European
practice, and its review needs to be completed. In addition, the lack
of
a final resolution of issues related to shared ownership of Krško NPP
may
affect the plant’s long term financial situation, and have an impact on
safety. Furthermore, the legal and financial situation of SNSA needs to
be improved in order to increase its independent safety assessment
capability.
Finally, the national response to nuclear and radiological emergencies
needs to be improved by implementing an integrated national emergency
plan,
paying special attention to the interface with the Croatian
authorities.
The SNSA, on its side, needs to develop further its own technical
capabilities
in order to be able to make better independent decisions, and needs to
continue defining its regulatory requirements to allow it to make the
licensing
decisions.
Nuclear power plant safety
status
Slovenia has one nuclear power plant located
in
Krško. The design of the Krško NPP is similar to other Westinghouse
PWRs
of the same type operating in the USA, Belgium, Switzerland, Korea and
Brazil. The safety of the Krško NPP is comparable to that of nuclear
power
plants of the same vintage into operation in Western Europe. The NPP
has
had a continuous backfitting and upgrading programme and a large
modernisation
programme, including the replacement of steam generators and a full
scope
simulator. The site organisation and the operational safety practice
are
similar to those in Western Europe.
For the future the following issues need to be
addressed. The implications on safety of the ownership for the long
term
and the upcoming privatisation process of the energy sector need to be
carefully assessed. In addition, efforts to strengthen the engineering
capability of the utility need to be continued, including resources to
ensure the necessary technical support from foreign organisations.
Closer
contacts with Western European utilities would also be beneficial.
Finally,
the evaluation of a few issues, like the seismic characterisation of
the
site and the onsite storage of spent fuel like need to be finalised and
further attention is deemed necessary to the performance of a periodic
safety review.
Detailed
chapters
BULGARIA
Chapter 1: Status of the
regulatory
regime and regulatory body
Status of the legislative
framework
-
The primary legislation for nuclear safety,
the Act
on the Use of Atomic Energy for Peaceful Purposes, was enacted in 1985
and amended in 1995 and 1998. Enforcing regulations, which give
interpretation
and meaning to the early primary legislation came into force in 1985
but,
due to shortage of resources, there has been slow progress in making
revisions
to reflect the 1995 and 1998 amendments. The Act gives responsibility
for
licensing and regulation to the Committee on the Safe Use of Atomic
Energy
for Peaceful Purposes (CUAEPP).
-
A Programme on the Development of a
Comprehensive
Legislative Framework on Safety of Spent Nuclear Fuel and Radioactive
Waste
Management was adopted by the Council of Ministers in December 1999.
-
A three-year programme for the development
and revision
of much of the present regulatory documentation was agreed in 1998 by
the
nuclear regulator and relevant Ministries. This will lead eventually to
greater consistency and facilitate the adoption of a less prescriptive
regulatory approach. However, the high workload of the regulatory body
means that this programme is already behind schedule and is likely to
be
delayed even further. In 1999 a new Act setting out further ambitious
amendments
to the earlier Act was developed by the CUAEPP in co-operation with
other
Ministries. However, this was rejected by the Council of Ministers in
February
2000, which will delay improvements in the legislative basis by at
least
one year. The proposed amendments aim to bring about the harmonisation
of the Bulgarian and West European legislation on the safety of nuclear
facilities and in the field of accounting and control of nuclear
material
leading to less prescriptive Bulgarian nuclear legislation. A new Act
on
the safety in the use of Nuclear Energy is under development by a joint
working group under the leadership of the CUAEPP. The new Act will
cover
in detail the management of radioactive waste, spent nuclear fuel and
decommissioning
of nuclear facilities. It will also establish a stable legal mechanism
for the financing of the regulatory body.
-
Existing legislation adequately defines the
legal
obligations of the Operator (Kozloduy NPP) giving it responsibility for
the safe control of the plant and for civil liabilities under the
Vienna
Convention. The primary legislation also requires the operating company
to make payments into funds for dealing with radioactive waste and for
decommissioning. The regulations to implement this came into force only
in 1999 and the first contributions to this fund were made in the same
year. Kozloduy NPP is wholly owned by the State.
-
All the key international conventions related
to
nuclear safety have been ratified and incorporated into national
legislation.
Status of the regulatory body
and
technical support infrastructure
-
The current legislation places a dual role on
the
CUAEPP. First as a State Body with membership from
organisations
concerned with the promotion of nuclear power and the operation of the
power stations, and secondly as a legal entity charged with
regulation
of safety. This implies a lack of independence of the CUAEPP as a
safety
regulator. The Council of Ministers decided in April 1999 that the
CUAEPP
should be replaced by an Agency of the Government, the State Atomic
Energy
Agency (SAEA). This would ensure regulatory independence from those
organisations
promoting nuclear energy and would give SAEA sole responsibility for
regulating
the nuclear facilities and the storage and transport of nuclear
material.
However, the legislation to implement this was rejected in February
2000.
-
Funding for the CUAEPP comes from the State
Budget
and is controlled by the Ministry of Finance. It is currently
inadequate.
Budget restrictions imposed in 1996 reduced the CUAEPP staff by about
25%
to 77. Of these, 50 posts were allocated to the Inspectorate on the
Safe
Use of Atomic Energy (ISUAE), the enforcement and inspection division
of
the CUAEPP. CUAEPP salaries are still approximately 20% of those in the
nuclear industry, and this makes recruitment and retention of well
qualified
staff difficult. Currently, there are not enough staff to adequately
carry
out all necessary safety assessment and site inspection duties and the
low salaries make the CUAEPP vulnerable to the loss of more experienced
personnel. The training for inspectors and succession planning will
need
to be improved when resources are available. A Council of Ministers
decision
in April 1999 approved step by step increase of the CUAEPP personnel to
88 in 1999, 102 (currently 80) in 2000 and a figure of 110 is under
negotiation
for 2001. Proposed legislation would fix the regulator’s salaries at a
minimum 80% of the equivalent industry level but this is not yet in
place.
Consequently the CUAEPP continues to lose staff.
-
In the past, frequent changes in senior
management
positions put additional strain on the CUAEPP. However, it is now
benefiting
from greater managerial stability, particularly with respect to the
position
of the Chairman. This is assisting the CUAEPP to plan and implement the
improvement process.
-
Existing legislation gives the CUAEPP some
enforcement
powers. Penalties for contravention of regulations are defined in the
primary
legislation. Enforcement relies heavily on fines. The CUAEPP also has
the
responsibility to authorise suppliers of equipment to the licensees.
-
The CUAEPP currently has limited resources to
perform
technical evaluations and relies to a considerable extent on external
support.
In the last few years local technical support organisations have
developed
in number and expertise. However, there are still only a limited number
in
the country, which means they are sometimes contracted to work for both
regulator and the utility. Following the enactment of the proposed new
national legislation, the CUAEPP intends to have a permanent body
dedicated
to the technical support of the regulatory authority. There is
currently
a need for continuing external assistance and this need for support is
unlikely to change in the near future.
-
The funds available to the CUAEPP for nuclear
safety
research and support are provided by charges levied on the licensees.
Compared
with equivalent funds typically available to Western regulators, this
is
at a fairly low level.
-
The status of the regulatory body is not yet
comparable
with its Western European counterparts. However, if political
commitment
would be achieved and resources made available, well-prepared plans
exist
to transform the CUAEPP.
Status of regulatory activities
-
An internally generated improvement plan
issued by
the CUAEPP in 1998 set out an ambitious programme for codifying the
CUAEPP’s
nuclear safety and licensing requirements. This will gradually replace
the prescriptive legacy of the former Soviet Union and bring the
Bulgarian
regulator in line with a Western European approach. The aim is to
create
a strong and independent regulatory body with sufficient funding to
carry
out the full range of regulatory activities, including the making of
regulations,
site inspection, assessment and enforcing the utility to implementation
of periodic safety reviews and draw up safety analysis reports as a
basis
for licensing. Some good progress has already been made, but
unfortunately,
because the CUAEPP has insufficient resources, implementation of the
plan
is already falling behind schedule. On the positive side, the CUAEPP is
making much better use of its site inspectors by adopting a Western
approach
in which the licensee carries out routine, qualification inspections of
pressure parts and lifting equipment, under a general supervision by
the
CUAEPP. The CUAEPP management has recognised the importance of
introducing
an internal quality management system and it is making progress in the
development of a manual and documents to support the regulatory work.
-
In general, the CUAEPP is staffed by
technically
competent personnel. However, since 1992, due to the limited resources,
the CUAEPP has had to rely on external independent technical
assessments
in carrying out the licensing of plant modifications and improvements.
Much of this has been provided under assistance projects funded by the
EC, the IAEA and bilateral programmes. In the absence of significant
increases
in CUAEPP resources, such assistance will continue to be needed, at
least
until the completion of the modernisation of units 5-6.
-
Regulatory decisions on the future upgrading
of the
Kozloduy units 1-4 need to be taken against a clear licensing plan
which
has yet to be fully established and implemented. This will require the
development of the relationship between the utility and a competent and
fully recognised regulator. At present the safety justification is
expected
to be completed in 2001. The CUAEPP needs to give clear guidance on the
compliance targets with consistency between initiating event
classification,
analysis assumptions and acceptance criteria.
Emergency preparedness on
governmental
side
-
In the past there were too many regulatory
documents,
produced over a number of years, to provide for an effective,
consistent
emergency response. A new Regulation for Emergency Planning and
Preparedness
for Actions in Case of a Radiation Accident was approved by a Decision
of the Council of Ministers in March 1999. This regulation defines the
responsibilities for planning, advising and decision making in the case
of a nuclear emergency. In October 1999 the CUAEPP started to up-date
the
National Emergency Plan for Action in Case of the Nuclear Accident at
Kozloduy
NPP. This is scheduled for completion at the end of 2000. The role of
the
CUAEPP will continue to be to monitor the situation and to give advice
to the central committee which takes the decisions. The CUAEPP has
received
international assistance in the development of its own Emergency
Preparedness
Manual. The CUAEPP has completed the modernisation of its Emergency
Response
Centre (ERC) with new offices, a diesel-generator for emergency power
supply
and new telephone and computer systems. Bulgaria is a participant in
the
IAEA Regional Assistance Project to promote harmonisation of emergency
planning in Central and Eastern Europe.
-
Currently, there are annual
communications-only exercises
involving all relevant national authorities, and there is a site
emergency
exercise each year. But the new emergency planning regulation requires
a full national nuclear emergency exercise every 5 years. A full
national
emergency exercise will be organised following the bringing into
operation
of the upgraded ERC. Bulgaria has participated in the last three INEX-2
international exercises organised by the OECD.
Conclusions
-
There have been significant improvements in
legislation,
organisation and operation of the CUAEPP. However, many of the
weaknesses
identified previously still remain. Lack of progress in several areas
is
no doubt partly due to the severe economic situation facing the
country.
Low wages, combined with a high workload and poor working conditions,
have
a negative effect on staff morale and the loss of further valuable
staff
is likely.
-
In order to reach Western European standards,
it
is recommended that the Government of Bulgaria considers the following
issues, several of which were addressed in the draft Act amending the
CUAEPP
that was rejected by the Council of Ministers in February 2000:
-
There is no substitute for a strong,
independent
and competent regulator. Over recent years, the technical competence,
strength
and continuity of the Bulgarian regulator has been strongly supported
by
Western experts. Major efforts are still needed to ensure that the
regulatory
authority achieves a status that is comparable with that considered
acceptable
in Western European countries. The independence of the CUAEPP from
bodies
concerned with the promotion and supply of nuclear power needs to be
made
explicit,
-
Managerial and organisational stability of
the regulatory
body should be maintained,
-
Budget and salaries for the CUAEPP need to
be increased
to allow it to recruit and retain sufficient numbers of competent staff
even though agreement has been given to increase staffing levels. In
addition,
the CUAEPP needs funds to obtain independent technical support when
required
and to support independent nuclear safety research,
-
There remains a shortage of competent
technical support
organisations within the country. The technical capabilities available
to the regulator need to be enhanced and should be independent from
those
used by the licensees.
-
In addition to the progress that has already
been
made, the CUAEPP needs to:
-
Ensure that sufficient resources are
committed to
continue the drafting and introduction of new and revised legislation
identified
in the CUAEPP Improvement Plan, and to the programme for codifying
CUAEPP’s
basic nuclear safety and licensing requirements.
Chapter 2:
Nuclear
power plant safety status
Data
-
On the site at Kozloduy, Bulgaria has in
operation
six nuclear power plants operated by the state owned company Kozloduy
NPP.
The Bulgarian Government has announced the closure of Kozloduy units 1
and 2 not later than 2003.
|
NPP unit
|
Reactor type
|
Start of construction
|
First grid connection
|
End of design life
|
Kozloduy 1
Kozloduy 2
Kozloduy 3
Kozloduy 4
Kozloduy 5
Kozloduy 6
|
VVER-440/230
VVER-440/230
VVER-440/230
VVER-440/230
VVER-1000/320
VVER-1000/320
|
1970
1970
1973
1973
1980
1984
|
1974
1975
1980
1982
1987
1991
|
2004
2005
2010
2012
2017
2021
|
-
On the Belene site, construction of two
VVER-1000/320
units was started in the 1980’s but the work was frozen in 1990.
(i) Kozloduy units 1-4
-
The main parts of the information summarised
in this
chapter are based on knowledge and experience acquired by the Technical
Safety Organisations (TSOs) during the Kozloduy short term upgrading
programmes
in the early nineties and during the TSOs assistance to the regulatory
body within the framework of EBRD's Nuclear Safety Account (NSA)
programme.
Information on more recent issues was
acquired
during the WENRA-Task Force Mission in October 1999.
Basic technical characteristics
Design basis aspects
-
The first four units on the Kozloduy site are
VVER-440/230
type nuclear power plants. Generic safety characteristics and safety
issues
of such plants are presented in Annex 2. Units 3 and 4 are more
advanced
type VVER-440/230 reactors having some of the design improvements of
the
later VVER-440/213. These include three-way redundancy and better
segregation
of safety systems, an Emergency Control Room and a low pressure core
cooling
system. During the early 1990's the utility implemented reconstruction
programmes on all units based on IAEA recommendations and TSO advice.
This
involved installation of additional safety systems with the objective
of
eliminating or diminishing major safety shortcomings. The aim of these
programmes was:
-
To establish the Reactor Pressure Vessel
status,
-
To improve the behaviour of the confinement
system,
-
To improve the plant behaviour in respect
of internal
and external hazards,
-
To improve systems and equipment
reliability,
-
To improve organisation and operational
safety.
Two further major items are being implemented on
a longer-term basis up to 2002:
-
To demonstrate the ability of the plant to
cope with
Loss of Coolant Accidents larger than the current (100 mm) Design Basis
using conservative analysis; the licensing analyses of the new design
basis
accident (200 mm) have been performed and are currently under review at
the CUAEPP,
-
To demonstrate the ability of the plant to
cope with
the complete rupture of a main primary coolant pipe (as Beyond Design
Basis
Accident) using best estimate analysis; analyses are expected to be
available
by the end of the year 2000.
Reactor pressure vessel and primary pressure
boundary
The current condition and the inspection
programme
of the reactor pressure vessels (RPV) appear adequate. The RPVs of
units
1 and 3 were annealed in 1989 and the RPV of unit 2 in 1992.
Measurements
of impurity concentrations in the weld near the core, and recent
experimental
results on irradiated samples taken from units 1 and 2 RPV, indicate
that
under the current design basis with postulated 100 mm break LOCA
further
annealing of RPV 1 and 2 would not be needed. However, investigations
of
additional samples seem to be necessary to confirm the re-embrittlement
behaviour. Whilst internal cladding prevents direct sampling of RPV 3,
it can be established from the original test coupons that chemical
composition
of the key weld of RPV 3 is bounded by those for unit 2. For unit 4,
lower
impurity contents in the affected weld mean that RPV embrittlement will
not be a problem during its operational life. As part of the revision
of
the design basis to a 200-mm break, an extended pressurised thermal
shock
analysis of the RPV is necessary.
The utility operating Kozloduy 1-4 has
implemented
measures to reduce the probability of a large primary circuit break.
The
present design basis covers pipe ruptures up to 100 mm including
primary
to secondary leakages in the steam generators (SG). Pipework above 100
mm, i.e. 200-mm pressurizer surge lines and 500-mm main coolant circuit
pipework, together with major primary circuit components such as main
coolant
pumps and valve bodies are covered by a state-of-the-art
leak-before-break
case (LBB). The LBB case has been performed by a Western industrial
company
under a Phare contract and has been accepted by the CUAEPP. The
proposed
extension of the DBA to cover ruptures up to 200 mm, if implemented,
will
provide some overlap between the prevention and mitigation measures.
The
calculations required to demonstrate fulfilment of LBB criteria for the
500-mm and the 200-mm primary circuit pipework have been carried out.
The
LBB case is underwritten by an in-service inspection programme and by
two
suitable instrumentation systems to detect incipient leaks. The LBB
criteria
commonly used in the Western countries require that three independent
reliable
and fast leak detection systems be used. A third independent system is
currently being considered to replace another less sensitive one. The
risk
of a large primary to secondary leak caused by a steam generator
collector
head lift has been reduced by the use of flow limiters and by specific
maintenance including in-service inspection. With the above-mentioned
installation
of the third leak detection system it is considered that the integrity
of the primary pressure boundary is safeguarded to an adequate level.
Confinement
Despite recent efforts that have led to
significant
reductions (by a factor of 10), the confinement system leak rate is
still
excessive, and effort is required to further reduce it. A necessary
confinement
improvement, the jet vortex condenser discharging through a water pool,
is planned to ensure the confinement's structural integrity in case of
large break LOCA accidents up to 500-mm breaks. Implementation on units
3 and 4 is planned for installation before 2002. This design solution
is
completely different from that already installed at Bohunice. However,
the jet vortex condenser still requires confirmation of the claimed
performance
and a proof of the absence of unwanted side effects under the whole
spectrum
of conditions. Therefore, for Kozloduy 1 and 2, implementation cannot
be
expected taking into account the declared shutdown dates of these units.
Safety systems and hazards
By 1997, with assistance from the EU (Phare)
and
Nuclear Safety Account, substantial short term safety improvements have
been implemented on all four units, e.g. improvements to reactivity
control
and additional reactor protection signals, measures to ensure the
integrity
of pressurised components, measures for improving protection against
hazards
in general (e.g. fire protection), and improvements to emergency power
supply. In order to provide reliable cooling of the reactor circuit a
new
emergency steam generator feed water system (2x200%) has been
implemented
for units 3 and 4. Extension of this system to units 1 and 2 was
provided
in the year 2000. This system allows the cooling down of the
corresponding
unit and maintaining it in the cold shutdown state. A primary bleed and
feed capability is available for all units. The steam lines are fixed
and
protected against multiple breaks in the non-isolatable part as well as
inside the turbine hall downstream the isolating valves. Upgrading for
protection against earthquakes is going on to achieve new seismic
requirements
of 0.2 g.
Units 3 and 4 are already equipped with a
low-pressure
core cooling system that facilitates Design Basis Accident extension.
Compared
to the VVER-440/213 type design, however, accumulators are absent and
ECCS
pumps and confinement spray pumps are located in the common boron
compartment
room.
I&C systems and emergency power supply
Replacement of safety related I&C
(Reactor Protection
System) will be necessary if it cannot be demonstrated that the
reliability
of the old relay based system complies with current international
standards.
It has to be noted that this replacement will be impractical for units
1 and 2 due to their limited residual lifetimes. The emergency power
supply
system fulfils international requirements, e.g. IAEA Safety Guides. For
each unit the system is redundant and single-failure proof, and the
equipment
is qualified for accidental conditions.
Beyond design basis accidents and severe
accidents
A series of safety improvements have been
introduced
in recent years in order to cope with some BDBA conditions such as the
installation of a new emergency feed water system, emergency feed water
supply by mobile pumps, implementation of equipment and procedures for
primary bleed and feed. Consideration should also be given to a
mitigative
severe accident management strategy when the prevention-related work is
reasonably complete.
Safety assessments and programmes for
further improvements
In the early 1990’s a consortium of Western
TSOs
assessed the safety status of units 1-2 and units 3-4 separately, and
reviewed
the corresponding modernisation programmes designed for safety during
short-term
operation. The TSO consortium gave recommendations for short-term
safety
upgrading measures under the condition of limited operational time,
which
were additional to those already identified by the utility.
In 1997 the utility proposed a more extensive
safety-upgrading programme for units 1-4. Several modifications have
already
been introduced, with the aim of operating these units up to the end of
their design life. This programme has undergone several updates, but
has
not been reviewed systematically by the regulatory authority. For
internal
review by the utility, a plant modification procedure exists in the
frame
of the NPP QA programme.
Safety assessment and documentation
The lack of Safety Analysis Reports (SAR) to
Western
standards for units 1-4 is a significant shortcoming, even though many
different analyses were performed in the past. In the early nineties,
international
ad-hoc teams or foreign expert organisations rather than Bulgarian
experts
carried out a major part of the safety assessment used as a basis for
safety
upgrades.
A limited number of (mainly) generic safety
analyses
are available for units 3-4. In support of the CUAEPP, Western TSOs in
collaboration with Bulgarian institutions have recently developed the
requirements
for a detailed Safety Report for units 3-4. This so-called Safety
Substantiation
Report (SSR) has to be provided to the regulator on completion of the
extended
modernisation programme (expected in 2002). The NPP has recently
submitted
a first revision of the Safety Substantiation Report for units 1-4 to
the
regulatory body. At present this report is undergoing a second revision.
Probabilistic safety assessment
Level-1 PSAs of varying levels of complexity
have
been carried out, considering the plant design status after short term
upgrading and covering initiating events at full power. Separate PSAs
for
units 1-2 and 3-4 were performed by Bulgarian institutions, in
collaboration
with those from Spain and Russia, partly based on generic data from
Russian
NPPs and also data from the IAEA. In the PSA for units 3-4 seismic
effects
and internal fires were also considered. At present they are in the
process
of verification after IPERS missions. A PSA level-1 for shutdown states
is currently underway. In-depth review is still outstanding.
Decommissioning
Bulgarian regulations, based on rules
inherited from
the former USSR, require the utility to provide documentation for
decommissioning
at least five years before the planned shutdown of a reactor. At
present
the preparation of technical proposals for units 1-2 decommissioning is
underway in the frame of a Phare project with completion planned in
2000.
Operational safety
-
There have been significant improvements in
the standards
of operational safety at all units and staff awareness of safety issues
has demonstrably increased.
Organisation, procedures, operation and
maintenance
- A number of upgrading measures have been
fully implemented
in Kozloduy units 1-4, or are well advanced:
-
The training of existing and new personnel
is now
based on a systematic approach; management training has been
introduced;
operating personnel now have access to a modern multi-functional
simulator
of the Kozloduy training centre with well trained instructors,
-
The technical specifications for operation
have been
significantly upgraded and are now unit specific,
-
Symptom-oriented accident procedures for
units 1-4
are under development in the frame of an international programme for
VVER-440/230
reactors and are planned to be implemented by the end of the year 2000.
Safety culture and management, quality
assurance
- Since 1992, with Western assistance to the
utility
and the safety authority, plant management has pursued the objective of
improving operational safety. The main goal of the management is to
motivate
personnel to continue the gradual increase in the safety and
reliability
of operation in order to reach a level comparable to Western practices.
Results of the OSART mission of the IAEA to Kozloduy units 1-4 in
January
1999 show that the status of operational safety has significantly
improved.
OSART gave a series of recommendations and encouraged NPP management to
continue these improvements. A follow up OSART mission was agreed for
the
end of 2000.
-
There is competent staff at the plant
dedicated to
the continuous safety upgrading process. The management structure has
been
reorganised, the responsibilities clearly defined, and a Quality
Assurance
(QA) programme established. In the past the utility and the plant
management
have made significant progress in the implementation of a modern safety
management system but improvements are still needed. In early 2000 the
structure of previous NPP management (EP-1 and EP-2) was reorganised
and
now the units 1-4 (VVER-440) and units 5-6 (VVER-1000) have a common
management.
-
The announcement of closure dates for units 1
and
2 present a new challenge for the utility and the plant management.
Appropriate
measures will be needed to ensure that motivation of staff for safe
operation
remains adequate during the remaining period of operation.
Operational experience
- A systematic analysis of operational
experience feedback
(from Kozloduy and from other PWRs) has been ongoing since the early
nineties.
Emergency preparedness
- There is an on-site emergency plan in
place. However,
the national approach to emergency planning as a whole is currently
under
review.
(ii) Kozloduy units 5-6
-
The statements presented in this chapter
regarding
the safety of Kozloduy units 5-6 are based on the knowledge gained
through
active TSO involvement in the plant modernisation, IAEA mission
records,
and the information received through the VVER regulators forum.
Basic technical characteristics
- The units 5-6 on the Kozloduy site are
VVER-1000/320
type nuclear power plants. Generic safety characteristics and safety
issues
of such plants are presented in Annex 2.
-
In principle, the main safety features of
units 5-6
are similar to the design of Western PWRs of the 1970’s. In the early
years
the units suffered from frequent disturbances mainly due to the low
quality
of some equipment. With the replacement of some control valves, such as
Feed Water control valves and a number of items of I&C and
electrical
equipment, as well as modification of the Steam Generators, a
reasonable
performance has now been achieved. This is important for safety because
the frequency of disturbances that might initiate an accident has been
reduced.
Safety assessments and programmes for further
improvements
- A plant specific safety assessment is not
yet available,
although insights gained from TSO assessments of similar plants (e.g.
Rovno
3) may be applicable to units 5-6. In developing the extended
modernisation
programmes for the VVER-1000 reactors, the utility has performed some
plant
specific safety analyses based on both deterministic and probabilistic
approaches. But it has also used IAEA recommendations and operational
experience
at similar plants.
-
The PSA for Kozloduy units 5-6 is the first
one performed
in Bulgaria by its own experts. It is a level-1 study covering
initiating
plant events at full power, and also including fire and seismic events.
It has undergone an IPERS mission review and a review by Western TSOs.
In the frame of the modernisation programme, the operating organisation
intends to adapt the PSA to the new plant status taking into account
the
TSO recommendations.
-
A programme for further upgrading of the
units 5-6
is at an early stage and has been reviewed by Western TSOs. The main
safety
improvements relate to fuel and control rod optimisation, long term
cooling
including measures for prevention of sump filter clogging, electrical
systems,
instrumentation and control, containment integrity and radiation
monitoring.
The programme involves major Western and Russian partners and is
planned
for completion in stages over the next few years. Safety assessments by
Western TSOs for similar plants in Ukraine and the Russian Federation
have
indicated that, after safety upgrading, it should be possible to
achieve
a level of safety in line with international recognised safety
practices.
However, to confirm this, a consistent safety case needs to be
established
and an adequate safety analysis needs to be made. Both will need to be
reviewed by the CUAEPP.
Operational safety
- Information and conclusions presented above
for the
Kozloduy 1-4 units are also generally applicable for units 5-6.
National industry
infrastructure
for technical support
-
In Bulgaria there are only limited resources
of independent
technical support organisations in support to Kozloduy NPP. These
include
Energoproject Sofia, several institutes of the Academy of Science,
Riskengineering,
ENPRO consult and BEQE.
On-site spent fuel and waste
management
-
Spent fuel of the VVER-440 reactors is stored
in
an on-site fuel store erected in the 1980’s. For the VER-440 units
there
is currently an agreement with Russia which permits transport of this
spent
fuel back to the Russian Federation. Presently the spent fuel store is
being modified to accept VVER-1000 fuel from units 5-6. This fuel is
currently
stored in pools within the containment and the storage space is nearly
full. Radioactive wastes originating at Kozloduy are stored in interim
storage
facilities and an on-site cementation plant for liquid wastes is being
built, although with considerable delay.
Conclusions
General remarks
- There have been significant improvements in the standards of
operational
safety at all units and staff awareness of safety issues has
demonstrably
increased.
-
The lack of SAR is a serious shortcoming for judging the safety of NPP.
Kozloduy units 1-4
- The short term upgrading measures implemented at units 1-4 have
significantly
improved the safety of these units. The measures taken so far have been
directed mainly to the prevention of incidents and accidents.
-
Despite the safety improvements already achieved and considering the
present
safety status of the plant, there are still some major safety issues
which
are closely linked to the original basic design of the VVER-440/230
reactors
and which are difficult to be removed. Among these are the limited
confinement
function and capability and the vulnerability against common cause
failures.
For Kozloduy 1-2 the implementation of relevant measures cannot be
expected
taking into account the announced closure dates.
-
Further safety improvements are being implemented or planned. The
current
safety-upgrading programme includes the extension of the design basis
to
a 200-mm break and the consolidation of the confinement system
improvements.
The utility and its technical support are motivated to the
implementation
of these improvements and have announced their intention to implement
safety-upgrading
programmes to mirror those that have been implemented at Bohunice V1.
However,
the work at Kozloduy is at least three years behind that at Bohunice
and
consequently safety improvement is not as far advanced.
-
In view of the large amount of work required to be carried out in the
next
modernisation stage it is difficult to have a final judgement on the
adequacy
and feasibility of all measures foreseen in this programme. It seems
that
financial provision for continued safety improvements are inadequate
for
Kozloduy 1-4.
Kozloduy units 5-6
- In principle, the main safety features of these units are similar
to Western
PWRs. A programme for further upgrading of these units is at an early
stage
and has been reviewed by Western TSOs.
-
Safety assessments done by Western TSOs for similar plants in Ukraine
and
Russia indicate that, with the completion of the planned safety
upgrades,
it could be possible to achieve a level of safety for units 5-6 that is
in line with international recognised safety practices. However, to
confirm
this, all safety measures from the programme have to be implemented and
a consistent safety case has to be established. Both have to be
reviewed
by the CUAEPP.
References
-
Convention on Nuclear Safety (CNS), Answers
to Questions
on the National Report of Bulgaria, April 1999.
-
International Conference on the Strengthening
of
Nuclear Safety in Eastern Europe, Vienna 14 - 18 June 1999, IAEA-CN-75.
CZECH
REPUBLIC
Chapter 1: Status of the
regulatory
regime and regulatory body
Status of the legislative
framework
-
A new Atomic Act (law on peaceful utilisation
of
nuclear energy and ionising radiation) came into force in 1997. It
confirms
the SÚJB as the responsible body for supervising the utilisation
of nuclear energy and ionising radiation. It defines the competencies
of
the SÚJB for the licensing of nuclear installations as well as
the
assessment, inspection and enforcement activities.
-
The Atomic Act states that the operator is
responsible
for the safety of its installations. The company that operates the
nuclear
power plants is a share holder company in which the state controls the
major part.
-
Since the new Atomic Act came into force in
1997,
the SÚJB has prepared or revised all regulations arising from
the
Atomic Act. The issuing of these regulations is an important
accomplishment
of the SÚJB.
-
The Czech Republic is a contracting party to
all
key international conventions dealing with nuclear safety.
-
The nuclear legislative framework in the
Czech Republic
is comparable with Western European practice.
Status of the regulatory body
and
technical support infrastructure
-
The SÚJB is a central agency of the
State
Administration reporting to the Government. Its President may
participate
in the meetings of the council of ministers. If needed, the Vice-Prime
Minister, in charge of economy and finance, ensures the link between
the
council of ministers and the SÚJB. The SÚJB is funded
from
the State budget, approved by the parliament.
-
The SÚJB is responsible for nuclear
safety,
radiation protection, transport of nuclear and radioactive material,
international
notification of incidents and accidents, the provision of information
to
the public, nuclear material accountancy, and the import and export of
dual purpose equipment. The SÚJB plays an important role in the
emergency preparedness and planning in conjunction with other
administrative
departments.
-
The SÚJB has the power to issue and
withdraw
authorisations. It also has the power to impose penalties on the
operators
for any violation of the conditions of an authorisation. Enforcement
actions
by individual inspectors can be appealed to the SÚJB President,
the next level of appeal being the court of justice.
-
The SÚJB considers that its current
budget
is sufficient. It obtained a 13% increase in 2000 to facilitate the
licensing
work for the Temelin nuclear power plant. The SÚJB has a special
budget for research, which is divided equally between radiation
protection
and nuclear safety. Certain administrative constraints arise for the
SÚJB
when it contracts for technical support. Except for small contracts or
matters that are urgent from a safety point of view, the SÚJB is
obliged to go through an open tendering process. This does not favour
the
long-term contractual technical support that the SÚJB needs.
-
The SÚJB was able to recruit 30 new
staff
over the last 3 years, which led to a total of 161 staff (as of 1st
January 2000) engaged on nuclear safety and radiation protection
activities.
The National Radiation Protection Institute, with a staff of 110
providing
technical support on radiation protection, is under direct SÚJB
supervision. From 1st January 2000 another TSO with 45 staff
came under the direct control of the SÚJB. Although its main
field
of operations is in the area of non-proliferation of nuclear,
biological
and chemical weapons, it also has considerable capabilities in the area
of radiation protection and emergency preparedness.
-
Technical support for nuclear safety is
provided
by the Nuclear Research Institute (ÚJV), Institutes of the
Academy
of Science of the Czech Republic, universities, private companies and
foreign
organisations (for example from Slovakia). But there are a limited
number
of experts available from within the Czech Republic, which leads to the
SÚJB needing to share competencies with the operators. Moreover,
the contracting procedures with which the SÚJB must comply
reduce
the possibility of having long-term contracts for dedicated regulatory
technical support. For the future, the SÚJB would prefer to
replace
some of the short-term contracts with individual contractors by
long-term
agreements with an extended scope of support. The administrative rules
should be adapted in order to make this possible.
-
It is considered that, in general, the
SÚJB
has a status comparable to that of Western European regulatory bodies.
Status of regulatory activities
-
Since 1992, a number of national and
international
evaluations of the SÚJB have taken place. The recommendations of
the various missions and support programmes have been used effectively
in the development of Czech regulatory activities. The SÚJB
takes
an active part in international regulatory co-operation.
-
The Atomic Act authorises the SÚJB to
draft
subordinate regulations which, after approval by a legal advisory group
of the Government, are signed by the SÚJB President. The laws
and
decrees issued in the Czech Republic contain very detailed
requirements.
The SÚJB needs to provide the Government with feedback on the
application
of the current regulatory pyramid and, if appropriate, propose the
necessary
changes. The SÚJB intends to continue developing technical
guidance
documents on the application of these regulations for the operators as
soon as resources are available after the licensing of the Temelin
nuclear
power plant.
-
A well-defined licensing process for nuclear
installations
according to Western practice has been set up in the Czech Republic. It
is governed by the Atomic Act and the Construction Act and includes the
steps of siting, construction, operation and decommissioning. Major
licences
for siting, construction and permanent operation are issued by the
District
Authorities of the region where the installation is located. Such
licences
cannot be granted if the SÚJB issues a negative opinion
regarding
the safety of the plant. The District Authorities collect opinions from
all other involved bodies of the state administration, including
SÚJB.
In addition to this process, there is a set of individual SÚJB
approvals,
which have to be granted (in accordance with the Atomic Act), for
individual
steps within the siting, construction, operation and decommissioning
phases
of a nuclear installation. The environment impact assessment, which is
part of the licensing process, includes a statement on the
decommissioning
options.
-
The methodology for assessment of safety
related
documentation is derived from US NRC practice. In addition to the
assessment
of the safety analysis reports, the SÚJB also assesses and
approves
such documents as plant technical specifications, the physical
protection
plan and the utility’s quality assurance programme. Requirements for
periodic
safety reviews are included in licence conditions, usually requesting a
review after 10 years of operation. However, when a plant is undergoing
a modernisation programme, the periodic safety review is regarded as
part
of that programme.
-
The SÚJB inspection activities also
derive
from US NRC practices. They are based on a biannual inspection plan.
The
inspection plan and the inspection committees are the foundation of the
SÚJB system of experience feedback. The SÚJB has
established
event-reporting requirements for the licensee and has developed a
system
for analysis and feedback of the licensee’s operating experience. This
is similar to Western European practice. The SÚJB also actively
participates in the INES and international event reporting systems. In
addition to its participation in the VVER regulators’ forum, the
SÚJB
has an international agreement with Slovakia and Hungary to share the
experiences
gained at Dukovany, Bohunice, Mochovce and Paks.
-
The SÚJB has established two advisory
committees,
one for nuclear safety, the other for radiation protection. This
provision
is recognised as a good practice. In addition, special advisors have
also
been contracted for the licensing of the Temelin nuclear power plant.
-
In summary, the SÚJB has developed a
series
of regulatory practices that compare favourably with those of Western
European
nuclear regulators. The SÚJB is giving high priority to the
licensing
of the Temelin nuclear power plant and will resume the development of
guidance
documents after this period of intensive activities.
Emergency preparedness on
governmental
side
-
The new Act in the field of emergency
preparedness
and planning was passed by the Parliament in June 2000. In the case of
an emergency situation of any kind, the co-ordination of all activities
is the responsibility of the Inter-Ministerial Crisis Co-ordination
Committee.
This is composed of sub-committees such as the one for protection of
the
public, of which the SÚJB President is a member.
-
In the case of a nuclear emergency, the
SÚJB
has a role to advise the authority responsible for the protection of
the
public. To this end it has created an emergency response centre.
-
On-site emergency plans are approved by the
SÚJB.
It also ensures their consistency with the off-site plans that are
approved
by the head of the District Authority.
-
Neighbouring countries, e.g. Austria, have
been invited
as observers during emergency exercises. The national organisation for
emergency preparedness needs to be further tested during exercises.
However,
the SÚJB considers that it will be difficult to test the
national
organisation in an exercise prior to the implementation of the new Act.
The Czech Republic has participated in INEX-2 international exercises.
-
It is concluded that the SÚJB has
taken the
appropriate steps to fulfil its role in emergency preparedness.
Conclusions
-
The regulatory regime and regulatory body in
the
Czech Republic are comparable with those in Western Europe. Nuclear
Safety
legislation establishes the roles and responsibilities of the utility
and
the regulatory body. The regulatory body is well engaged in the state
control
of nuclear activities and the national emergency organisation is
defined.
A well-defined licensing process according to Western practice has been
set up in the Czech Republic.
-
It is recommended that the Government of the
Czech
Republic consider the following:
-
The implementation of the new Act on
emergency preparedness
and planning needs to be given a high priority,
-
It seems that the documents in the regulatory
pyramid
in some cases may contain too detailed requirements. The SÚJB
should
be requested to suggest simplifications,
-
The contracting rules of the SÚJB need
to
be adapted so that it can obtain, when appropriate, the necessary high
quality technical support on a long term basis.
Chapter 2: Nuclear power
plant safety status
Data
-
The Czech Republic has two nuclear power
plants (NPP)
at Dukovany and Temelin. Temelin NPP is the only plant within EU
candidate
countries, which is not yet in operation. Fuel loading of unit 1
started
on 5 July 2000, fuel loading for unit 2 is planned to be approximately
15 months later.
|
NPP unit
|
Reactor type
|
Start of construction
|
First grid connection
|
End of
design life
|
Dukovany:
(in operation)
Unit 1
Unit 2
Unit 3
Unit 4
|
VVER-440/213
VVER-440/213
VVER-440/213
VVER-440/213
|
1974
1978
1978
1978
|
02/1985
01/1986
11/1986
06/1987
|
2015
2016
2016
2017
|
Temelin:
(under construction)
Unit 1
Unit 2
|
VVER-1000/320
VVER-1000/320
|
1986
1987
|
Fuel loading
07/2000
11/2001
|
Design lifetime
30 years
30 years
|
-
The plants are owned by CEZ a.s. (Czech Power
Company),
a joint stock company. CEZ is the sole license holder for the
construction
and operation of nuclear power installations in the Czech Republic.
(i) Dukovany units 1-4
-
The information given in this report on
Dukovany
NPP is based on the general knowledge on VVER-440/213 plants
(summarised
in Annex 2), the Czech National Report for the Convention on Nuclear
Safety
(April 1999), IAEA documents and information provided by the
SÚJB
and the NPP.
The plant specific technical statements
mainly
rely on information provided by the operator on the occasion of a two
days
expert meeting with the SÚJB and the operator in June 1999 at
Dukovany.
Major safety issues were discussed and a summary list of upgrading
measures
(already implemented or planned in the near future) was provided by the
operator. A second meeting of TSO expert organisations with the
regulatory
authority and the operator took place in May 2000. Since Dukovany NPP
was
not supported by large Western TSO projects in the past, both expert
meetings
were most worthwhile in providing technical information on the safety
status
of the NPP. Other background documentation which has been used is
listed
in the references.
An in-depth safety assessment of Dukovany
NPP,
in particular a review of the modernisation programme (MORAVA), has not
been made by Western TSOs. The operator, however, offered to give
further
help in confirming and expanding the technical information on the
plant's
safety status given so far.
- The initial design lifetime for each unit
as a whole
is 30 years from first criticality. For each of the reactor pressure
vessels
the design lifetime is 40 years.
Basic technical characteristics
Design basis aspects
- All units of Dukovany NPP are second
generation VVER-440/213
type reactors. Generic safety characteristics of these reactors are
presented
in Annex 2.
-
For the primary circuit and the
safety-related systems,
the basic design was made by Russian organisations. The specific plant
design was developed and carried out by Energoprojekt Prague, a Czech
company
which, under Czech law, became the only responsible organisation for
the
design. All major parts of the primary equipment (except the main
circulation
pumps) as well as the equipment of the whole secondary circuit were
manufactured
in the former Czechoslovakia, mainly by Skoda Plzen, Vitkovice, etc.
Domestic
companies were also engaged in the quality control during manufacturing
and construction. Since the nineties fuel manufacturing in Russia is
also
under Czech quality control. No major quality concerns have been
identified
in tests and inspections carried out since start of operation. Since
the
first years of plant operation, safety improvements have been made
continuously.
A major back-fitting programme had already started in 1991 based on the
safety assessment of Greifswald unit 5, analyses and supporting
programmes
of the IAEA and WANO, and other international co-operation. Major
safety
improvements were focussed on fire protection, electrical supply,
secondary
side feedwater supply, and the installation of an emergency response
centre.
Further improvements are either under design or planned.
Reactor pressure vessel and primary
pressure
boundary
- Reactor pressure vessel integrity
(especially safety
margins against radiation embrittlement) appears to be adequate for all
units. Due to the well-balanced composition of material impurities (low
content of Phosphorus, Copper) and the protection measures to lower the
embrittlement rate, it is expected that annealing will not be necessary
for any of the vessels during the design lifetime. To ensure pressure
vessel
integrity various measures have been introduced, e.g. low leakage core
configuration and pressure vessel embrittlement monitoring by a
surveillance
programme. In-service inspections of the reactor pressure vessels and
the
primary piping are conducted with state-of-the-art techniques.
-
The piping systems were designed in
accordance with
Russian and Czech standards. A set of primary pipe whip restraints has
been partially installed. A partial leak-before-break (LBB)
implementation
exists, but it is not relied upon in the safety case. Several
preventive
measures on steam generator (SG) integrity have been implemented or are
underway (e.g. N16 activity measurement on each steam line, measures
for
exclusion of corrosion damage at flange connections, new feedwater
distributors
(inside the SG) in order to exclude primary collector thermal fatigue).
Accident analyses have been performed and corresponding emergency
operating
procedures have been revised.
-
After completion of pipe whip restraints, the
integrity
of the primary pressure boundary is considered to be adequately safe.
Confinement
- The leak rates have continuously decreased
since
the commissioning but they are still slightly higher than those that
are
usually accepted in Western PWR containments. For design basis
accidents,
however, radiological consequences would not exceed those accepted
within
EU countries. The performance of the bubbler condenser system in case
of
Large Break LOCA has been verified in full-scope tests in the frame of
the Bubbler Condenser Experimental Qualification project sponsored by
the
EU. The test results for Large Break LOCAs were reported in early 2000.
There is still need for detailed analysis of the experimental project
results
and for complementary tests for other design basis accidents.
Safety systems and hazards
- In terms of capacity and redundancy the
design of
the safety systems is in general comparable to Western reactors of the
same vintage (see Annex 2). Several measures against hazards (e.g. fire
protection) have been taken in order to improve the separation between
redundant trains. Further upgrading protection measures are completed
or
under way. Protection against sump screen clogging has been
implemented.
Secondary pipe whip restraints are scheduled to be added at the 14.7-m
level in accordance with US standards, based on results of a recent
analysis.
-
For improving the original generic
VVER-440/213 design
at Dukovany NPP, an independent Emergency Feedwater System has been
installed
in a separate building. Former shortcomings have been eliminated.
-
A systematic fire hazard analysis and a
flooding
analysis were carried out in 1997. Major weak points already have been
eliminated (e.g. fire prevention measures). Further measures are
underway
or planned to be completed in 2000. Measures to cope with high-energy
pipe
breaks are under development, the completion is scheduled for 2003.
-
Seismic qualification of existing equipment
is ongoing
in the frame of the MORAVA Project; all new implemented equipment is
qualified
to withstand 0.1g which is acceptable for this site according to
Western
practice.
I&C systems and emergency power supply
- Many improvements on I&C and electrical
equipment
have already been introduced or are underway. Based on insights gained
from reliability analyses, proposals for modifications in the safety
related
I&C have been developed and will be implemented in 2001. Under
current
plans of the utility major upgrading of the I&C with digital
systems
is foreseen by 2010.
-
Various means for condition monitoring of
mechanical
components, e.g. vibration monitoring of reactor internals, lose part
monitoring,
on-line operational load measurement as well as ageing monitoring for
key
components, have been introduced.
Beyond design basis accidents and severe
accidents
- Analyses on some representative beyond
design basis
accidents (e.g. ATWS, total loss of heat sink, total loss of electrical
power) were completed in 1998. The results of these analyses were used
in the development of symptom based emergency operating procedures.
Analyses
on selected severe accidents with core melt scenario have been
performed
within the scope of a regional Phare project and in the frame of a
level-2
PSA.
Safety assessments and programmes for further
improvements
Safety assessment and documentation
- In 1991 the former Czechoslovak Atomic
Energy Commission
(CSKAE) established conditions for licensing unit 1 for continued
operation
beyond 10 years (after 1994). In particular, this required the operator
to provide a revised SAR, the so-called Operational Safety Analysis
Report
(OSAR). OSARs also have been prepared for units 2-4. Based on the OSAR,
the SÚJB issues time-limited licences for further operation.
The structure and content of the OSAR are in
compliance
with the Regulatory Guide n°5 from 1988 and, to a major extent,
with
the later IAEA guide for periodic safety reviews (IAEA Safety Series
50-SG-O12).
- All the modifications and safety
improvements implemented
at Dukovany NPP have to be included continuously in the safety analysis
reports of the corresponding unit.
Probabilistic safety assessment
- In 1992 the first version of a level-1 PSA
study
for Dukovany NPP was developed by Nuclear Research Institute Rez (NRI),
in co-operation with several Czech and Slovak research institutes. In
1994
the updated level-1 PSA for Dukovany NPP was completed. The study was
the
first level-1 PSA completed for a VVER-440/213 reactor by a Western
contractor.
Since 1995 NRI has regularly updated the Dukovany level-1 PSA under a
living
PSA project. The current version of the level-1 PSA includes internal
initiating
events, fires and floods. The results were used for confirmation and
scheduling
of upgrading measures within the scope of the MORAVA programme (see
§
24) and for refining of the emergency operating procedures. Finally in
1998 the level-1 PSA study was reviewed by an IAEA IPERS mission.
-
In addition, a shutdown PSA (SPSA) has been
carried
out. The results of the SPSA indicate that the contribution to the
total
core damage frequency is comparable with that of operation at full
power.
The results of the SPSA are being used to improve procedures for shut
down
accidental conditions. First results of a level-2 PSA study are already
available and they will be used as an input for severe accident
guidelines.
Safety measures and further assessments
- The Dukovany NPP is involved in
international co-operation.
Several IAEA missions (OSART, ASSET, IPERS, etc.) have been performed
to
assess plant operational safety.
All important safety issues have been
addressed
in the existing safety programme and are either resolved or are
underway.
It is intended that the relevant measures will be resolved according to
a schedule and will be complete by the year 2002 [1].
- The Dukovany NPP is practising an extensive
exchange
with WANO and participates in common activities with other VVER-440/213
operators.
Programmes for safety improvements
- An extensive modernisation programme
(MORAVA) has
been established based on Western nuclear safety standards and
evaluation
of operational experience [2]. The whole modernisation programme will
be
fully implemented by 2010. The major safety modifications, except
I&C,
will be completed by 2004. Upgrading of the safety related parts of the
I&C with digital systems is planned to be implemented during
refuelling
outages and will be complete by 2010. The main objective of the
programme
is to achieve a safety level that is fully comparable with
international
safety standards and NPPs operating in EU countries.
-
Major upgrading measures which have already
been
implemented or are under way are for example:
-
Automatic protection against primary
circuit cold
overpressure,
-
Protection against sump screen clogging,
-
Modification of equipment on the 14.7-m
floor as
pipe whip restrains, protection against missiles, replacement of
valves,
two additional steam relief valves, replacement and re-routing of pipes
are under way,
-
Modifications on the emergency feedwater
system (e.g.
pipe whip restraints, qualification of valves, et al.) are underway.
Furthermore, additional measures for
assuring
safe operation are underway, e.g.:
-
Reconstruction and extension of diagnostic
monitoring
equipment,
-
Installation of a full scope simulator.
Reconstruction of the I&C system is
under
preparation.
Operational safety
Organisation, procedures, operation and
maintenance
- Staff responsibilities within the NPP are
clearly
defined. Nuclear safety and production are separate divisions within
the
management organisation. The head of the nuclear safety division is a
deputy
director.
-
Until now the plant operational personnel
have been
trained at the full-scope simulator of the VUJE Education and Training
Centre (Slovakia). At Dukovany, a plant specific full-scope simulator
has
been installed and training is planned to start there from the
beginning
of 2001.
-
Symptom oriented emergency operating
procedures (EOPs)
have been developed in co-operation with Westinghouse. The new EOPs
were
fully introduced in November 1999.
Safety culture and management, quality
assurance
- The safety culture of Dukovany NPP has been
continuously
improved. Two OSART missions in 1989 and 1991 noted a high level of
nuclear
safety and a professional management with competent and trained
personnel.
A WANO peer review was performed in 1997.
-
A comprehensive quality assurance programme
(QA)
was established in compliance with IAEA recommendations and regulatory
requirements. A management system has been set up in order to assess
the
safety significance of plant modifications and to ensure their proper
implementation.
Operational experience
- The reliability of plant operation since
its first
start-up is an indication of the good quality of the equipment.
-
Over the last ten years the average number of
unplanned
shutdowns (scrams) per unit has been less than 1 per year. A system has
been established to ensure efficient feedback of operational experience
from Dukovany NPP and other NPPs, especially from VVER reactors.
Emergency preparedness
- The emergency plan is regularly updated and
exercises
are carried out annually. The Dukovany Crisis Centre is equipped with
necessary
computerised support systems. The level of preparedness achieved is
adequate.
(ii) Temelin units 1-2
-
Originally it was planned to build 4
VVER-1000 type
reactors at Temelin. Construction of the first two units started in
1986.
In the early 1990s the original plan, however, was revised. In 1993 the
former government decided to complete only units 1 and 2. This decision
was re-approved last year by the current government.
-
Background information on Temelin NPP is
available
from several IAEA documents and to some extent from bilateral
co-operation
with institutions from EU countries. Furthermore additional generic
information
on the main safety features of VVER-1000 derives from Tacis and Phare
projects
on other VVER-1000 plants (e.g. Rovno 3, Kozloduy 5-6).
Several IAEA documents have been used for
the
assessment given in this chapter, e.g. IAEA report on VVER